 The Works Continue

Stage 1 — Demolition of the existing Boiler Room, prefab. classroom, kitchen dining area and hall, all located to the west of the site.

Start May 2016 and complete July 2016. Stage 2 — The build of the new Primary School. Start July 2016 and complete Aug 2017 Stage 3 — Demolition of the existing main school and the construction of a new sports pitch and hard/soft landscaping. Start Aug 2017 and complete April 2018.

Stage 1 — Now complete.

Stage 2 — Current status:

• The external envelope is complete and final roofing works are taking place. • Groundworks in the courtyard are nearing completion and landscaping works have started as you can see in the photos.

• The internal fit-out is almost complete. Floor finishes and decorations are continuing. Kitchen equipment is installed.

• The main hall high-level ceiling grid and vinyl flooring are complete and the folding screen and climbing walls are due to start. • Mechanical and electrical commissioning is taking place and M&E equipment familiarisation training for the school is scheduled for this month. • Client inspections have started and will continue as areas are completed allowing for phased handover.

• Decant of the existing building furniture starts at the end of this month.

Weald Rise Primary School Residents’ Newsletter - Issue 15 July 2017

Site Hours & Delivery Times Site hours will be 0800 to 1800hrs Monday to Friday.

It may be necessary to undertake some works on a Saturday if so this will be between 0800 to 1300hrs.

During term-time there will be no site deliveries permitted between 0830hrs-0915hrs and 1515hrs-1630hrs Completed façade and flood wall External signage in progress As part of the Kier Group Vision 2020 Challenge Kier Group Vision 2020 Challenge Kier Group Vision 2020 Challenge the site team completed an 11.5 mile cycle on the 2nd June 2017 from Weald Rise Primary School to Nottingdale School in support of the Kier Foundation and its partner charities.

For more information on the charities we are supporting, please visit the links below: Alzheimer’s Society: https://www.alzheimers.org.uk/

Great Ormond Street Hospital: https://www.gosh.nhs.uk/

Haven House Foundation: https://www.havenhouse.org.uk/

Should you wish to make a donation please visit the following link to make donations to the Kier London – link to make donations to the Kier London –Weald Rise Weald Rise Primary School team who will be completing this challenge. this challenge.